Development Update: Week of January 18, 2021


January 18th, 2021

DEVELOPMENT UPDATE:
Marriott International Headquarters & Marriott Hotel

Week of January 18, 2021

In the new year, significant progress continues in downtown Bethesda at the development site of the future Marriott International Headquarters and Marriott Hotel.

On the exterior façade, installation of the curtain wall and continues and is expected to reach the roof of the office building by the end of January. The entire glass curtain wall is anticipated to be complete this spring. Along Wisconsin Avenue, the installation of the lobby’s glass wall has begun with structural supports, and glass placements are expected to begin in February.

Inside the buildings, the buildout continues with the installation of mechanical, electrical, and plumbing work ongoing, and with a total seventeen elevators inside the office building, and another five inside the hotel, several elevators are now complete.

On the office building’s rooftop, additional roofing and miscellaneous steelwork continue through January, where the installation of the green roof has also begun. Hovering above the office building, the tower crane is scheduled for removal by the end of January.

Meanwhile along Woodmont Avenue, the telecommunications infrastructure is now complete and awaiting the installation of telecom cables. The only remaining underground work includes the installation of new traffic signaling.

 

Virtual Community Meetings

The development team is committed to an open dialog with the Bethesda community and holds monthly virtual community meetings that are open to the public, where you are invited to join the team online for a live presentation and Q&A of the latest construction updates.

Our next virtual community meeting will be held Tuesday, February 2, at 6:00 PM EDT. More information and links to join will be shared in a future update.

Prior to the next community meeting, we encourage you to submit any development and construction-related questions and comments to development@mhqbethesda.com, or call (240) 514-7831.

 

Watch Construction Time-Lapse

You can see a live construction camera featuring a 24/7 time-lapse view of the development site.

View camera »

 

 

Have a Question or Comment?

For questions, contact Barney Silver, Vice President, Construction at Boston Properties; or Alex Paschalides, Project Manager at Hensel Phelps. Please send your email to development@MHQBethesda.com or call (240) 514-7831 to leave a voicemail message.