Development Update: Week of May 13, 2019

NOTICE OF CONSTRUCTION ACTIVITY Marriott International Headquarters Week of May 13, 2019: Underground utility improvements and restoration work continues along Woodmont Avenue and are anticipated to continue through July. Work at the intersection of Woodmont and Norfolk Avenues is currently being completed during nighttime hours to minimize potential impact on neighboring businesses, traffic and pedestrians. […]

read more


Marriott’s Casey Oakes Joins Small Business Network Panel

Casey Oakes, Director of Supplier Diversity at Marriott International, recently appeared on the latest Small Business Network panel hosted by Montgomery Community Media. The panel, moderated by Taylor-Leonard Corporate CEO Kelly Leonard, also included Anna Hakobyan of AstraZeneca, and Karen Zuckerman of HZ. The Small Business Network is designed to bring the business community together to […]

read more


Development Update: Week of May 6, 2019

NOTICE OF CONSTRUCTION ACTIVITY Marriott International Headquarters Week of May 6, 2019: Underground utility improvements and restoration work continues along Woodmont Avenue and will continue through July. As the work at the intersection of Woodmont and Norfolk Avenues is quite extensive, this work is currently being completed during nighttime hours to mimize potential impact on […]

read more


Development Update: Week of April 29, 2019

NOTICE OF CONSTRUCTION ACTIVITY Marriott International Headquarters Week of April 29, 2019: Underground utility improvements and restoration work continues along Woodmont Avenue and will continue through July. As the work at the intersection of Woodmont and Norfolk Avenues is quite extensive, it will be completed during nighttime hours beginning this week to mimize potential impact […]

read more


Development Update: Week of April 22, 2019

NOTICE OF CONSTRUCTION ACTIVITY Marriott International Headquarters Week of April 22, 2019: Mass excavation and hauling operations continue from Wisconsin Avenue. It is anticipated that these operations will continue through July with concrete operations beginning in mid-May. Throughout this project, the approved Montgomery County and State Highway traffic control plans will ensure minimal impact to traffic […]

read more


Development Update: Week of April 15, 2019

NOTICE OF CONSTRUCTION ACTIVITY Marriott International Headquarters Week of April 15, 2019: Earlier this month, the ramp into the construction site for mass excavation and hauling operations was relocated from Woodmont Avenue to Wisconsin Avenue, significantly reducing construction traffic along Woodmont Avenue. It is anticipated that these operations will continue through July with concrete operations […]

read more


Development Update: Week of April 8, 2019

NOTICE OF CONSTRUCTION ACTIVITY Marriott International Headquarters Week of April 8, 2019: As of this week, the ramp from Woodmont Avenue has been relocated to Wisconsin Avenue for the mass excavation and hauling operations. In the near future, blasting of bedrock may be required for which advance notice will be provided. It is anticipated that […]

read more


Development Update: Week of April 1, 2019

NOTICE OF CONSTRUCTION ACTIVITY Marriott International Headquarters Week of April 1, 2019: The development team’s revised schedule for all noise-related construction activities began last week. This effort to minimize the impact on neighboring residents and businesses, as well as commuters passing through the area, has addressed many concerns about disruption and inconvenience. Coverage of the […]

read more


Marriott brings awareness to climate change with #MIEarthHour

Tonight, in honor of Earth Hour 2019, Marriott associates from more than 7,000 hotels will join millions of people around the world to dim and turn off non-essential lights for one hour to bring awareness to the threat of climate change.

read more


Bethesda Magazine: Woodmont Avenue Utility Work for Marriott Headquarters Shifts to Mornings

Mar. 26, 2019 – Developers of the Marriott International headquarters office tower in downtown Bethesda have adjusted the construction schedule for utility work on Woodmont Avenue to accommodate nearby residents, with noise-related activities shifting to the morning hours. » Read more at bethesdamagazine.com

read more