Development Update: Week of August 31, 2020


September 2nd, 2020

NOTICE OF CONSTRUCTION ACTIVITY
Marriott International Headquarters

The Latest Construction Update
Week of August 31, 2020

Following the announcement that the hotel building topped-out, the construction of the new Marriott International Headquarters and Marriott Hotel is fast approaching its next major milestone. Construction of the office building continues next door and is expected to top-out in early November 2020.

Work continues around the base of the construction site with the noisiest activities, such as saw-cutting, taking place only during the day. Next week, on Tuesday, September 8, nighttime work is expected to resume along Woodmont and Norfolk Avenues, as heavy excavation equipment will facilitate the installation of future telecommunications and signaling duct banks this fall. This work is expected to last no later than the end of October. No lane closures are expected as part of this work.

Meanwhile, concrete pouring operations continue and are expected to be completed this fall, as the installation of curtain wall and glass continue to rise up along the exterior façade of both buildings. Inside, every trade contractor, including mechanical, electrical, plumbing, masonry and others, are hard at work inside both the office and hotel buildings.

 

Virtual Community Meetings

The development team is committed to an open dialog with the Bethesda community and holds monthly virtual community meetings that are open to the public, where you are invited to join the team online for a live presentation and Q&A of the latest construction updates.

Our next virtual community meeting will be held Tuesday, October 6, at 6:00 PM EDT. Please join us online at that time by selecting this link.

Prior to the next community meeting, we encourage you to submit any development and construction-related questions and comments to development@mhqbethesda.com, or call (240) 514-7831 to leave a voicemail message.

 

Your Safety Around the Construction Site

Throughout this project, approved Montgomery County and State Highway traffic and pedestrian control plans ensure minimal impact to traffic flow around the construction site. Along Woodmont and Norfolk Avenues, walkways with overhead protection now allow for uninterrupted pedestrian access throughout the project. Pedestrian access is now aided by wayfinding signage at the entrances of these covered walkways. Along Wisconsin Avenue, pedestrians are redirected to use the east sidewalk for their safety. Access along the west side has been closed following State Highway approvals. For available walkways around the construction site along Woodmont, Norfolk, and Wisconsin Avenues, view the pedestrian site logistics plan here. The safety of commuters and pedestrians around the construction site is vitally important, so we ask that you please be vigilant and pay close attention to detour signs and flagging operators as they help to ensure your safety, direct traffic, and minimize disruptions.

 

Watch Construction Time-Lapse

You can see a live construction camera featuring a 24/7 time-lapse view of the development site.

View camera »


More News from Marriott International:

Thoughts on Leading Through a Crisis

From Marriott International President & CEO Arne Sorenson

“This global crisis is far from over. But still, I remain optimistic about the future. With the help of leaders – in government, in business and in the non-profit space – around the world, we’ll get through this – by listening, empowering others and communicating our plans.”

 

Have a Question or Comment?

For questions, contact Barney Silver, Vice President, Construction at Boston Properties; or Alex Paschalides, Project Manager at Hensel Phelps. Please send your email to development@MHQBethesda.com or call (240) 514-7831 to leave a voicemail message.