Development Update: Week of June 29, 2020


July 1st, 2020

NOTICE OF CONSTRUCTION ACTIVITY
Marriott International Headquarters

The Latest Construction Update
Week of June 29, 2020

The office building’s 13th floor is being finished, just as the hotel building reaches its 12th floor. The project approaches a major milestone as the hotel building is scheduled to top-out in July.

Deliveries of the curtain wall and glass continue for the exterior façade of both buildings, and installation is already underway. Along both Wisconsin Avenue and Woodmont Avenue, hoists are now operational on the office building and hotel building respectively to facilitate the delivery of materials. In addition to the covered walkways, netting has now been installed throughout the building to protect from the unlikely chance of any falling debris.

Meanwhile, contractors are hard at work with mechanical, electrical, plumbing, masonry, and more inside both the office and hotel buildings. Outside, preparations are being made for the installation of telecommunications ductbanks along Woodmont and Norfolk avenues, which is anticipated to begin in the coming weeks.

 

Virtual Community Meetings

The development team is committed to an open dialog with the Bethesda community and holds monthly virtual community meetings that are open to the public. Held the first Tuesday of each month, you can join the team online for a live presentation and Q&A of the latest construction updates.

Our next virtual community meeting will be held Tuesday, July 7, at 6:00 PM EDT. Please join online at that time by selecting this link.

Prior to the next community meeting, we encourage you to submit any development and construction-related questions and comments to development@mhqbethesda.com, or call (240) 514-7831 to leave a voicemail.

 

More News from Marriott International…

  • Marriott International’s Response to Racial Injustice
    In a statement published by Marriott International, Executive Chairman & Chairman of the Board J.W. Marriott, Jr., President & Chief Executive Officer Arne Sorenson, and Global Chief Human Resources Officer & Global Chief Diversity Officer David Rodriguez shared their thoughts on the important conversation happening across the United States right now on racial injustice. In the statement, Marriott’s leadership reminded the public of the company’s culture of inclusion and beliefs in equality, justice, and putting people first. Read the statement here.

 

  • Marriott International Recognized for Contributions to Pandemic Response
    As part of the Maryland Unites initiative of Maryland Governor Larry Hogan’s office, which provides a website with key information about how Marylanders can volunteer and help others during the coronavirus pandemic, Marriott International has been recognized for its contributions to the pandemic response. The company teamed up with American Express Co. and JPMorgan Chase & Co. to provide approximately 100,000 room nights at its hotels to medical workers working on the front lines of caring for those affected by the coronavirus.

 

Your Safety Around the Construction Site

Throughout this project, approved Montgomery County and State Highway traffic and pedestrian control plans ensure minimal impact to traffic flow around the construction site. Along Woodmont and Norfolk Avenues, walkways with overhead protection now allow for uninterrupted pedestrian access throughout the project. Pedestrian access is now aided by wayfinding signage at the entrances of these covered walkways. Along Wisconsin Avenue, pedestrians are redirected to use the east sidewalk for their safety. Access along the west side has been closed following State Highway approvals. For available walkways around the construction site along Woodmont, Norfolk, and Wisconsin Avenues, view the pedestrian site logistics plan here. The safety of commuters and pedestrians around the construction site is vitally important, so we ask that you please be vigilant and pay close attention to detour signs and flagging operators as they help to ensure your safety, direct traffic, and minimize disruptions.

 

Watch Construction Time-Lapse

You can see a live construction camera featuring a 24/7 time-lapse view of the development site.

View camera »

 