Development Update: Week of April 22, 2019

NOTICE OF CONSTRUCTION ACTIVITY
Marriott International Headquarters

Week of April 22, 2019:

Mass excavation and hauling operations continue from Wisconsin Avenue. It is anticipated that these operations will continue through July with concrete operations beginning in mid-May. Throughout this project, the approved Montgomery County and State Highway traffic control plans will ensure minimal impact to traffic flow around the construction site.

Underground utility improvements and restoration work continues along Woodmont Avenue and will continue through July. As the work at the intersection of Woodmont and Norfolk Avenues is quite deep, this work will be completed during nighttime hours to minimize potential impact on traffic and pedestrians. At all times, two-way traffic will be maintained as often as possible.

The timeline for all upcoming phases of the utility work is estimated in the attached site plan. Please note, this plan does not include anticipated work performed by Pepco.

Meanwhile, sidewalk closures remain in place along sections of Woodmont, Norfolk and Wisconsin Avenues (view map of closures here). Additional temporary closures will be necessary during this time. Pedestrians will be detoured to the east sidewalk of Wisconsin Avenue during work hours and should take advantage of nearby crosswalks as needed. Please be vigilant and pay close attention to signage as detours may change occasionally. Our number one priority is the safety and security of pedestrians and commuters in and around the construction site.

\


 

Monthly construction updates

The developers and general contractor are committed to an open dialog with the community and they hold bimonthly construction updates for the general public. These updates are generally scheduled for the first Tuesday of every other month and take place in downtown Bethesda at the Bethesda-Chevy Chase County Regional Services Center, on the second floor in rooms A and B, located at 4805 Edgemoor Lane, Bethesda, MD 20814.

The next update will take place Tuesday, June 4 at 6:00 p.m.

 

Watch live construction time-lapse

You can see a live construction camera featuring a 24/7 time-lapse view of the development site.

View camera »

 

For questions, contact Barney Silver, Vice President, Construction at Boston Properties; or Gavin McDuff, Area Superintendent at Hensel Phelps. Please send your email to development@MHQBethesda.com or call (240) 514-7831 to leave a voicemail message.