Development Update: Week of Feb. 18, 2019

NOTICE OF CONSTRUCTION ACTIVITY
Marriott International Headquarters

Week of February 18, 2019:

This week, contractors will begin performing nighttime underground utility improvements and restoration work (paving) along Woodmont Avenue. This work is anticipated to continue through July 2019. During this time, sections of the southbound lane may be closed for utility access, but two-way traffic will be maintained as often as possible.

The development team has released the following site plan that outlines estimated dates for each phase of the work, including future phases along Wisconsin and Norfolk Avenues. Please note, this plan does not include anticipated Pepco work to be performed during this time.

 

Meanwhile, excavation and hauling activities will continue for the next several months. Blasting of the bedrock will likely commence in March, and concrete pouring operations will likely commence in May.

Throughout this time, the Montgomery County and State-approved traffic control plans will ensure minimal impact to traffic flow around the site. Sidewalk closures remain in place along sections of Woodmont, Norfolk and Wisconsin Avenues (view map of closures here), and additional temporary closures may be necessary during this time. Pedestrians will be detoured to the east sidewalk of Wisconsin Avenue during work hours and should take advantage of nearby crosswalks as needed. Please be vigilant and pay close attention to signage as detours may change occasionally.

 


 

Monthly construction updates

The developers and general contractor hold bimonthly construction updates for the general public. These updates are generally scheduled for the first Tuesday of every other month and take place in downtown Bethesda at the Montgomery County Regional Service Center, on the second floor in rooms A and B, located at 4805 Edgemoor Lane, Bethesda, MD 20814.

The next update will take place on Tuesday, April 2 at 6:00 p.m. Please note: the previously scheduled meeting in March has been cancelled.

 

Call our Development Hotline

Nearby residents, businesses, commuters, and other interested parties seeking reliable information about the progress of the Marriott International headquarters development site may call our Marriott HQ Development Update Hotline. In addition to the information already available from the MHQBethesda.comwebsite and development update e-blasts, now you can call and leave a voicemail for the development team.

To leave us a message, call (240) 514-7831.

 

Watch live construction time-lapse

You can see a live construction camera featuring a 24/7 time-lapse view of the development site.

View camera »

 

For questions, contact Barney Silver, Vice President, Construction at Boston Properties; or Gavin McDuff, Area Superintendent at Hensel Phelps. Please send your email to development@MHQBethesda.com or call (240) 514-7831 to leave a voicemail message.